GET IN TOUCH

Westfield

Due to the Westfield retail center being a live site to the public, works could only be carried out at specific times. Making this project extremely important to safety and scheduled programe times. Pro Site were the first strip out company to have 4 proto type battery mini dumper to be used in a retail mall environment. Pro Site have one of only two battery powered mini floor chiselers in the UK; a specialist piece of equipment. Pro Site were contracted directly to Westfield Special Projects. The manufacturers of our min dumpers have make a promotional presentation to best illustrate this equipment. A clean site was handed over.

On completion of the retail floor area being previously stripped out by Pro Site;1000m2 of screed was removed.

  • Project Value – £ 26k
  • Duration of works – 10 Nights
  • Out of hours shifts – 02:30am till 06:30am
  • 1000m2 of screed broken up and removed
  • Team – 8 Men
  • Pro Site specialist battery powered breakers and mini dumpers used
  • Total Screed Waste Cleared -240 Tonnes
  • Site Safety – Vibration control log