Harris – Reading

A 3000 square meter strip out over two floors including all, power, data, partitioned and folding walls, comms/data room and staff canteen. This site was stripped out in full and had a conditional re-fit by the principal contractor. The duration of this project was 8 weeks for the initial strip out and clearance of all waste from site. All waste was removed via the comunial staircase, making this project labour intensive.

  • Project Value – £115k
  • Duration of Works – 8 Weeks
  • Repeat Projects for Principal Contractor – 3rd by Pro Site
  • Part Cat “B” Landlord office strip out
  • Team – 12 Men
  • Total Waste Cleared – 178 Tonnes
  • Site Safety – 100%