Putney Station

This bar/restaurant premises was completely stripped out, ready for a planned refit by Urban Leisure Group. Strip Out were tasked to strip out and remove all shop fixtures, fittings,commercial kitchen with extraction system and all WC blocks. A complete strip out of the dry lined walls, MF ceiling and wooden flooring was carried out. The AC system were de-gassed and removed. A clean site was handed over.

  • Project Value – £16k
  • Duration of Works – 14 Days
  • Complete Cat “A” bar / pub strip out
  • Team – 5 Men
  • Specialists – AC degas & F-Gas recovery
  • Total Waste Cleared – 31 Tonnes
  • Site Safety – 100%