GET IN TOUCH

Meridian, Chelsea

This hi-end retail unit was completely stripped out as per landlords specification, ready for planned new lease letting contract. Strip Out were tasked to strip out and remove all fixtures and fittings. A complete strip out of the dry lined walls, MF ceilings and carpet flooring were carried out. All power, AC, data and alarms systems were removed. A clean site was handed over.

  • Project Value – £6k
  • Duration of Works – 4 Days
  • Hi-End retail strip out back to Cat”A”
  • Team – 3 Men
  • Total Waste Cleared – 7.5 Tonnes
  • Site Safety – 100%