Jimmy Choo Westfield was a partial store soft strip out. Pro Site carried out this fast strip out requirement in a challenging working department store with complex operating procedures. A complete strip out of the dry lined walls, MF ceiling and tiled flooring was carried out. All power, alarms and data were removed. A clean slab to slab was handed over. This project was done on behalf off the clients preferred shopfitting contractor. The new store now open.
- Project Value – £ 10k
- Duration of Works: 4 Days & 1 Night
- Full retail strip out back to shell core
- Team – 4 Men
- Total Waste Cleared – 8.5 Tonnes
- Site Safety – 100%