This central London Hugo Boss store was completely stripped out, ready for a new tenant re-fit. Pro Site were tasked to strip out and remove all shop fitting fixtures and fittings. A complete strip out of the dry lined walls, MF ceiling and tiled flooring was carried out. All power, alarms and data were removed. A clean slab to slab was handed over.
- Project Value – £16k
- Duration of Works – 10 Days
- High-end Retail strip out back to build base core
- Team – 5 Men
- Total Waste Cleared – 38 Tonnes
- Site Safety – 100%